client:
Acoustic map of the city of Świętochłowice
Customer: Świętochłowice City Hall
Task: "Acoustic Map of the City of Świętochłowice"
Scope of work:
- Measurement of acoustic loading in the area of the city of Świętochłowice
- Elaboration of an Acoustic Map of the City of Świętochłowice in conformity with requirements defined by Act of April 27, 2001 – Environmental Protection Law and Directive 2002/49/EC of the European Parliament and of the Council relating to the assessment and management of environmental noise
- Implementation o fan IT system with a digital map application based on a GIS platform
- Assessment of the environment acoustic condition in the entire area of the city of Świętochłowice
client:
Hermanowice - Strachocina high pressure gas pipeline
Customer: Investgas S. A.
Task: "Elaboration of project documentation of DN700 Hermanowice - Strachocina high pressure gas pipeline"
Scope of work:
- Elaboration of eco-physiographic studies and environmental impact forecasts for the needs of changes in the studies of conditions and directions of spatial development for the communes of: Sanok, Tyrawa Wołoska, Bircza, Ustrzyki Dolne, Fredropol
- Elaboration of the project information
- Elaboration of documentation – Environmental Performance Report – and being granted a decision of the project environmental conditions
- Investor’s representation in the course of administrative proceedings and co-operation with the RDOŚ [Regional Directorate for Environmental Protection]
- Creation of a wildlife inventory
client:
Resolving of a problem of asbestos waste contamination in Ogrodzieniec
Customer: County Office [Starostwo Powiatowe] in Zawiercie
Task: “Elaboration of a complex solution to the problem of asbestos waste contamination in an area owned by the Treasury in the commune of Ogrodzieniec”
Scope of work:
- Ecological review of an illegal waste disposal site
- Feasibility study
- Author’s supervision
- Demolition project
- Project of waste disposal site remediation
- Project documentation of closing of the illegal waste disposal site, and documentation of site remediation,
- Complete application with required annexes for the National and District Environmental Protection Fund and Waste Management
client:
Katowice International Airport in Pyrzowice
Customer: Katowice International Airport in Pyrzowice
Task: "Concept and project and construction documentation of aprons of the surface of 140 000 m2 for the aircrafts at Katowice International Airport in Pyrzowice”
Scope of work:
- Waste and sewage management concept in the area of the designed apron
- Environmental performance report
- Statement of water management conditions
- Construction projects of stormwater drainage and water plants
- Working plans and specifications for stormwater drainage and water plants
- Bills of quantities, cost estimates and technical specification for stormwater drainage and water plants
Task: "Defining of a limited use area"
Scope of work:
- Elaboration of a complete application for defining of a limited use area
- Measurements of acoustic loading in the limited use area
- Implementation of an IT system with a digital map application based on a GIS platform
- Agreeing of the project with the authorities of Silesia District
client:
Kielce Regional Airport
Customer: Kielce Regional Airport
Task: "Elaboration of environmental documentation for the needs of the airport infrastructure extension”
Scope of work:
- Waste and sewage management concept
- Documentation for application for the permit required by the Water Law Act
- for the area of Kielce – Obice Airport and a quarry in the area of Kamienna Góra
- Environmental performance of the project: macro leveling of the area of Kielce – Obice Airport and the quarry in the area of Kamienna Góra
- Environmental performance of the project: The Construction of Kielce - Obice Airport
- Concept of water intake with a water treatment plant and a pump station
- Concept of municipal sewage treatment plant for the needs of Kielce – Obice airport
client:
Mazovian Airport Sochaczew
Customer: Mazovian Airport Sochaczew
Task: "Elaboration of environmental documentation for the needs of the airport infrastructure extension”
Scope of work:
- Documentation enclosed to the environmental performance report, indispensable for defining of a limited use area
- Inventory and valorization of wildlife to elaborate the environmental performance report and to analyze potential compensation measures in the scope of wildlife, cost analysis of possible proceedings
- Methodology of studies in the fields of ornithology and chiropterology for the environmental performance report including research and inventory works
- Statement of water management conditions for the construction of water plants
client:
Waste incinerator in PKN ORLEN S. A. in Płock
Customer: Veolia Water Systems Sp. z o.o.
Task: "Elaboration of documentation for a recycling and neutralization plant of wastes, including dangerous ones located in the area of PKN ORLEN S. A. Production Facility in Płock"
Scope of work:
- Application with a complete documentation indispensable for being granted the integrated permit
- Application with a complete documentation indispensable for being granted the permit required by the Water Law Act
- Investor’s representation before relevant administrative bodies, including participation in social consultations necessary in the process of granting to the investor of a plant utilization permit
client:
Modernization of waste incinerator
Customer: Sarpi Dąbrowa Górnicza Sp. z o.o.
Task: "Development and modernization of thermal waste treatment plant"
Scope of work:
- Environmental performance report
- Application for a change in the integrated permit
- Emissions and noise immissions measurement
- Analyses of the existing technical and formal condition and of possibility of boosting the plant capacity to 50 000 Mg/year
- Representation before relevant administrative bodies, participation in the decision-making process with the administrative body, and complex consulting services in the scope of environmental protection until adequate decisions are granted
client:
Medical waste incinerator
Customer: Centrum Onkologii - Instytut im. Marii Skłodowskiej - Curie, oddział w Gliwicach [The Maria Skłodowska-Curie Institute of Oncology – Branch Gliwice]
Task: "Modernisation of the existing plant for thermal neutralization of medical waste in the waste treatment plant and the boiler house"
Scope of work:
- Construction project for the incinerator extension concept
- Environmental performance report
- Air protection study
- System of constant emission and immission monitoring
- Waste management study
client:
Co-generation and alternative fuel
Customer: Przedsiębiorstwo Gospodarki Komunalnej [Public Utilites Company] „EKOM” Sp. z o.o. in Nysa
Task: “Extension of the existing unit for production of alternative fuel with fitting of installation for the production of energy in congregation”
Scope of work:
- Environmental performance report
- Feasibility study
- Complete application for co-financing realized in the framework of Operational Program Infrastructure and Environment, Priority Axis II – Waste management and land surface protection